Amirkabir NATM Tunnel- A case study of design challenges in a mega project of tunnel in soft ground

Files in This Item:
File Description SizeFormat 
5_040.pdf1.32 MBAdobe PDFDownload
Title: Amirkabir NATM Tunnel- A case study of design challenges in a mega project of tunnel in soft ground
Authors: Golshani, Aliakbar
Moradabadi, Ehsan
Permanent link: http://hdl.handle.net/10197/7465
Date: 4-May-2013
Abstract: In spite of enhancement in modeling techniques as well as site investigation methods, uncertainty exists seriously in the process of construction of underground structure in soft soils. These uncertainties arise from limited data of geological data, measurement errors, interpolation of spatially geological properties, and extrapolation of results of experiments and natural analogue studies over times and conditions relevant to the project. Robust and optimize design of tunnel support pattern consists many important parameters including advance rate and excavation method. However, quantitative definition of these parameters is difficult because of restricting in site investigation data and uncertainties related to them. Furthermore, erroneous evaluation in these parameters can affect in incorrect projection of tunnel stability or economic loss. The work reported in this paper specifically dealt with Amirkabir highway tunnel with approximately 1.5Km long in each tube (i.e.,north and south tubes).It is one of the important projects excavating below one of the highest traffic region of Tehran, including the difficulty of excavating through a heterogeneous sedimentary basin mainly composed of recent alluvial. Construction has been performed by different methods i.e., Underground excavation, Cut and Cover and Top/Down methods in different sections of the project. Deformations and settlements have been monitored during and after construction in order to avoid unpredictable deformations and as a result any possible failure. Similar to other part of the project, a probabilistic hypothetical elasticity modulus (PHEM) approach has been employed to evaluate the uncertainty in lining design of a horseshoe shape NATM(New Austrian Tunneling Method) tunnel in T4 section of the project.The hybrid model, PHEM, consisting two essential parts is used to evaluate the performance of the system. A MATLAB interface program for generating the ABAQUS-based parametric model in one hand; and a Monte Carlo algorithm (Latin Hyper Cube Sampling method) to simulate the uncertainty existed in the system on the other hand are applied to produce the probabilistic density function of surface settlement of tunnel excavation and lining phases. In comparison with the monitoring data, the numerical results show that the PHEM approach introduced has had an appropriate prediction in surface settlements, improved the classical deterministic approaches.
Type of material: Conference Publication
Publisher: Distance and Continuing Education, Missouri University of Science and Technology
Keywords: Probabilistic hypothetical elasticity modulus approachNATM TunnelingUncertainty managementReliability analysis
DOI: 10.13140/RG.2.1.2532.0807
Language: en
Status of Item: Peer reviewed
Conference Details: Seventh International Conference on Case Histories in Geotechnical Engineering and Symposium in Honor of Clyde Baker, Chicago, USA, 29 April 4 May 2013
Appears in Collections:Civil Engineering Research Collection

Show full item record

Download(s) 50

108
checked on May 25, 2018

Google ScholarTM

Check

Altmetric


This item is available under the Attribution-NonCommercial-NoDerivs 3.0 Ireland. No item may be reproduced for commercial purposes. For other possible restrictions on use please refer to the publisher's URL where this is made available, or to notes contained in the item itself. Other terms may apply.